The final construction of the Hoonah greenhouse was constructed in phases. https://www.hia-env.org/2025/04/21/in-one-year-a-new-greenhouse-arose-in-hoonah/ These phases were segregated in ways that were fundable with a mix of funding depending on the intent of the funding. Our funding scheme had specific needs to linked to specific funding.
Foundation/pex –
The site was prepared by HIA by flattening it and packing it down. HIA purchased the rebar and pex for the foundation pour. HIA then procured a local contractor to complete the work.
Procurement for this item was a first hurdle in the construction of the greenhouse. We put the project/need out for bids to several contractors. The first bids we received were 3-4 times above what we expected to receive. Ultimately we were patient and received another bid from a contractor capable of doing the work that was within our budget.
We poured a foundation with pex installed and fully reinforced with rebar. The final foundation was based on the specifications in the greenhouse design and incorporated the civil engineering drain structure.




Assembling the building –
The greenhouse kit came contained within two, 40-foot connex containers on a barge. This step was another large hurdle in procuring a contractor as we received bids that were far, far above the cost we could afford with the funding we have. However, we were able to reach a contract with the same contractor that poured the foundation and then proceeded with the construction of the building.
The building came with assembly instructions which were used by the contractor to assemble it. However, it shouldn’t be underestimated the amount of time and problem solving it took to build the structure. Construction began in May and concluded in July.


Digging water infrastructure –
HIA undertook digging in the water infrastructure with our own staff and equipment. We were capable of doing the work ourselves and this was a significant cost savings. We had to install water drainage to grade and code to service the greenhouse
Electricity hookups –
Upgrading our panel – The electricity demand of a greenhouse of our scale is significant and in our case we had to upgrade our feed to accommodate the load of the greenhouse. We were sure to work through professional electricians to complete the electrical upgrades within our panels and feed. The greenhouse is fed by a 600 amp panel.
Installing the biomass heater –
HIA installed an outdoor boiler for our greenhouse. We buried the insulated water lines so they could not be affected by frost. The heater is a HeatMaster C250 capable of 250,000 BTU.
The boiler is a continuing challenge point for our operation. The size of it makes the stoking process frequent. Our heat storage is not adequate the provide a consistent heat profile to the greenhouse. This results in high peaks and lows in the greenhouse and requires the propane heater to come on to meet inconsistent heat from the boiler. The boiler must be stocked every 8-10 hours resulting in odd hours when it has to be stoked and not providing for consistent heat over time

Installing the propane heater –
Propane heaters were installed at either end of the building. These were provided in the design of the greenhouse and in the kit when it was shipped. The propane heaters are meant to be a backup to the primary, biomass heating system
Screens and keeping bugs out –
The original kit did not ship with bug screens but we installed a large screen housing over the air intake in the back. This screen did not function well and one of the challenges we experienced in the greenhouse after 6 months of operation was an aphid outbreak. In 2026, we corrected this by installing a better screen encasing over the intakes in the back. During the 2026 season we did not have any bug outbreaks, which we hope are a testament to the screens. We also purchased from the greenhouse manufacturer a screen to be installed into the roof vent area of the greenhouse. This is to mitigate bugs coming in through the ridge vent when it is open.

Funding and total cost –
The total cost to build and operate this greenhouse should not be underplayed. Our total construction cost was around $750,000. Some of the costs of construction and operation are included below. Our program is supported by grants and revenue from sales but also from BIA base funding as well at the BIA 105L Leasing Program.
Construction
Greenhouse Kit – $120,000
Towers $635 each x 90 = $57,150
Foundation = $85,000
Facility Assembly/Erection $250,000
Bato Buckets $5,639 each x 2 = $11,279
Boiler – $40,000
Heating – $12,000
Fridge $2,000
Operation
Coordinator – $100,000 year with full benefits package
Marketing – $70,000 with full benefits package
Electricity $90,000/year @ 0.65/kwh with peak usage happening in the winter when the lights have to be on
Propane – 100lbs/week during the winter if not using wood
Wood Consumption – Estimate at 15 cords/year